Ask for an FAT evidence pack that can be traced from the approved documents to the tested machine state and finished samples. At minimum, identify the drawing revision, trial material, setup record, test sequence, labeled samples, measurement results, deviations, corrective actions and sign-off status. Video and photographs support the record but do not replace measured evidence.

Stacked roll-formed profile samples retained for factory acceptance review
FAT evidence reviewStacked roll-formed profile samples in our Xiamen production base. Identified physical samples are one part of FAT evidence; the complete record should also link each sample to the approved drawing, trial material, setup, measurements, deviations and sign-off.

Freeze the documents before testing

List the approved drawing, machine scope, electrical standard and acceptance method used for the FAT. If a document changes during the test, record the revision and the effect on the remaining checks.

Identify the trial material and machine state

Record steel grade, thickness and coil or sheet identification when available. Connect the material to the final tooling, guide, recipe and cut-off settings. A video without this context cannot prove that the ordered condition was tested.

Keep labeled output and a deviation log

Label samples so measurements, photographs and videos can be traced to the same run. Record failed or incomplete items, the agreed corrective action and whether re-test evidence is still required before shipment.

Buyer review checklist

Review itemEvidence to recordWhy it matters
Approved documentsDrawing, scope and acceptance revisionDefines what the test is intended to prove
Trial materialGrade, thickness and material IDConnects the result to the tested input
Machine stateTooling, recipe, guides and cut-off setupMakes the accepted condition traceable
Output evidenceSample IDs, measurements, photos and videoCombines visible and measured results
Open itemsDeviation, owner, action and re-test statusPrevents incomplete points from disappearing

Questions buyers ask

Can a factory video replace an FAT report?

No. Video can show sequence and visible operation, but it normally does not provide complete material identity, setup values or measured acceptance results.

Should buyers request every machine parameter?

Request the parameters and evidence defined by the order, risk assessment and acceptance plan. Do not create arbitrary limits that were not agreed.

What happens when an FAT item fails?

Record the deviation, responsible party, corrective action and required re-test evidence. Shipment status should follow the contract and written approval process.

Information to send for an order-specific review

Provide the profile drawing, steel grade, thickness range, punching layout and target output. Add the destination electrical standard and the required acceptance method when they affect the line scope. These inputs allow a supplier to discuss the actual application without inventing a configuration from a generic catalogue model.

Related technical references

cut-off station checklist · setup documentation guide · quotation checklist

Source and scope: Halcyon Machinery photograph from our Xiamen production base, dated 2026; technical guidance reviewed 22 September 2026. The photograph is contextual evidence only. Order-specific dimensions, ratings, tolerances, safety scope, price and delivery require written confirmation.

Leave your email for a technical follow-up

Review guarding and isolation evidence before accepting a line layout or trial. A photo is context, not evidence that the quoted safety scope is complete.